Current projects in the VENA area, last updated August 28, 2010 | |||
| Project | Location | Plans, etc | Status, issues |
| Vacation of Signal Road Project #1006520 |
Signal Road from Barstow to Ventura Boulevard |
August 26, 2010 letter from D.R. Horton's contractor May 17, 2010 letter from Hope to DRB Request to vacate Signal Plan for Alameda alignment Opinion poll results (updated 10/20) |
August 2010: The developer for the portion north of Desert Vista is requesting another extension - this time 3 months. See the letter at the left.
The DRB heard a request on 10/21/09 for the vacation of Signal from Carrington to Ventura. The request for vacation was denied because it was not shown how this would benefit the community. There was no appeal. The trustees for the Hope Episcopal are now exploring a request for a hearing to vacate just the portion from Carrington to Mendocino. |
| Eubank Boulevard widening | Eubank Boulevard from Academy to Paseo del Norte | October 2009 Newsletter with plan from Bernalillo County | Bernalillo County is beginning a major project. Eubank from San Antonio to Paseo del Norte will be two lanes each way with a median. |
| North Domingo Baca City Park | Northwest of the intersection of Wyoming and Carmel | Presentation | We have a dog park, a skate park, and a playground so far. The groundbreaking ceremony for the Multi Generational center will occur on Thursday Oct 1 at 7520 Carmel NE; near the corner of Wyoming and Carmel at 11 AM. RSVP to Teresa Sanchez at 764-6469 if you plan to attend. Funding for the park is on the October 6 ballot. |
| Ventura Plaza Project number 1006602 |
Southwest corner of Paseo del Norte and Ventura | Plan Elevation Landscaping |
Walgreen's expects to open their doors on Wednesday, 10/28. There is no other contruction planned at this site at this time. |
| Hope Episcopal Church | Between Signal and Alameda, between Barstow and Ventura | Plan | The Church is completed and holding services. The healing center and parish hall do not have start dates yet. They are waiting on a resolution of the issue of whether or not Signal will be closed from Carrington to Ventura. When this is resolved they can complete their Signal frontage. |
| 9100 Holly Project number 1000523 |
Triangular lot north of Albertson's | no plans | This land was repossessed by the owner's bank. VENA contacted the city zoning enforcement office about the debris, the fence, etc. The city cleaned up the lot and put an lien on the property for the cost. |
| Hope Plaza | Between Signal and Alameda, between Barstow and Ventura | Elevation | We think this project is completed. |
| Vintner Court | Between Vineyard IV and Wilshire Boulevard | Plan | These six homes appear to be completed. |